What is a schedule of values, and how does it drive pay applications?

A schedule of values is a breakdown of the total contract price into line items, usually by trade or by specification division, that the contractor and owner agree on before work starts. Each month the contractor bills against those lines with a pay application, which in the AIA format is a summary sheet (G702) and a continuation sheet (G703). The continuation sheet shows the percent complete and stored materials on every line, retainage is held back, and the summary sheet turns the totals into the amount due this period.

TL;DR

  • The schedule of values (SOV) splits the contract sum into lines. Once the owner and architect accept it, it is effectively locked, and every pay application draws against the same line numbers.
  • In the AIA format, the G703 continuation sheet holds the line-by-line detail and the G702 application and certificate for payment summarizes it. The summary has to tie to the detail, or the application comes back.
  • Retainage is a percentage of completed work and stored materials that the owner holds until later in the project. It is subtracted on the summary sheet to reach the amount due.
  • Stored materials can be billed only if the contract allows it, and the materials must be properly stored and insured. Check the contract and expect to supply documentation.
  • A worked example below builds a six-line schedule, computes the totals and shows the payment due with 10% retainage. A second example compares what was billed with revenue earned under the percentage of completion method.
  • Billing and revenue recognition are different things. Overbilling and underbilling show up on the WIP report, and this guide explains where the two meet.
  • The numbers in the examples are illustrations built for this guide. The AIA forms are copyrighted, so we describe their structure and do not reproduce them. Confirm accounting treatment with your CPA.
  • CommercePundit connects field progress to billing and reporting for contractors. See the last section.

What is the schedule of values?

Think of the schedule of values as the menu the contractor agrees to bill from. The contract sum is divided into lines, such as mobilization, site work, concrete, structural steel, mechanical and electrical rough-in, and finishes, with a dollar value on each. Many teams number the lines by CSI MasterFormat divisions so everyone can find them. The owner and architect review it before the first payment, and it matters more than it looks, because it sets how fast the contractor gets paid.

A schedule that is front-loaded, with more value assigned to early work than the work is worth, gets the contractor paid sooner and exposes the owner if the contractor walks away. A schedule that is back-loaded does the opposite. Reviewers watch for this, and a balanced schedule, where each line reflects the real cost and a fair share of overhead and profit, makes the whole process smoother. Once accepted, the lines should not be changed casually. Changes to the contract arrive as change orders, which normally get their own lines or adjust existing ones in a documented way.

How do the G702 and G703 work together?

The AIA pay application is two documents that must agree. The G703 continuation sheet is the detail. For each schedule of values line it records the scheduled value, the work completed in previous applications, the work completed this period, materials presently stored and not yet installed, the total completed and stored to date, the percentage complete, the balance to finish and the retainage. The G702 application and certificate for payment is the summary. It takes the totals from the G703, adds change order totals to arrive at the current contract sum, subtracts retainage and previous payments, and shows the current payment due.

The most common reason an application is rejected is that the two do not reconcile. If the summary total does not tie to the sum of the detail lines, or retainage is calculated differently in each place, the architect sends it back and the contractor waits another cycle for money. Column letters differ between versions of the forms, so use your own version for line-by-line instructions. The AIA publishes guidance on completing them, and because the forms are copyrighted this guide describes the structure and leaves the forms themselves to the source.

How are retainage and stored materials handled?

Retainage is a percentage of each payment, commonly set in the contract, that the owner holds back as security until the work is complete or a defined milestone is reached. On the summary sheet it usually appears as separate lines for retainage on completed work and retainage on stored materials, and the total is subtracted from the amount earned. The rate, any reduction after a milestone and the timing of release are contract terms, and state law can limit them, so read the contract rather than assuming a standard.

Stored materials are items the contractor has bought and has on site or in an approved location but has not yet installed. A contractor may be able to bill for them, but only if the contract permits it, and owners typically want evidence: invoices, photos, proof of insurance and a secure storage location. Many teams also attach lien waivers from subcontractors for the previous payment. On prevailing wage jobs the billing package also has to square with certified payroll reports, so keep the two in step. Missing paperwork is the second most common reason a pay application sits unpaid.

Worked example: one month of billing on a $1,000,000 contract

Here is a small invented project with a six-line schedule of values, 10% retainage on completed work and stored materials, and billing in the second month after the first application covered mobilization, site work and part of the concrete and steel. Every figure is an assumption, and your forms will arrange the columns differently.

Line Scheduled value Previous This period Stored Completed and stored Percent Balance to finish
Mobilization $50,000 $50,000 $0 $0 $50,000 100% $0
Site work $150,000 $150,000 $0 $0 $150,000 100% $0
Concrete $300,000 $120,000 $90,000 $0 $210,000 70% $90,000
Structural steel $250,000 $50,000 $100,000 $25,000 $175,000 70% $75,000
MEP rough-in $150,000 $0 $30,000 $15,000 $45,000 30% $105,000
Finishes $100,000 $0 $0 $0 $0 0% $100,000
Total $1,000,000 $370,000 $220,000 $40,000 $630,000 63% $370,000

Total completed and stored to date is $630,000, which is 63% of the contract. Retainage at 10% is $63,000, so the total earned less retainage is $567,000. The previous application certified $370,000 of work, which after 10% retainage means $333,000 was already paid. The current payment due is therefore $567,000 minus $333,000, or $234,000. If a change order of $40,000 had been approved, the contract sum would rise to $1,040,000, the new work would be added as its own line and each total would flow through the same way.

Notice how much of the month’s billing comes from stored materials: $40,000 of the $260,000 of new billing, which is the sum of this period’s work and the stored items. That portion is the first to be questioned if the paperwork is thin, so it is worth having invoices, photos and insurance evidence ready in the same package.

How does billing relate to the percentage of completion method?

A pay application is a billing document. It is how the contractor asks for cash. The percentage of completion method is an accounting approach to deciding how much revenue to recognize on a long-term contract. In its common cost-to-cost form, the percent complete is the costs incurred to date divided by the total estimated costs, and revenue recognized is that percentage multiplied by the contract price. The two numbers are usually close but are rarely identical, and the difference is what the WIP report is designed to show.

Take the same project. Suppose the contractor now estimates total costs of $850,000 and has incurred $520,000. Cost-to-cost percent complete is 61.2%, so the revenue earned is about $611,765. The contractor has billed $630,000, which means the project is overbilled by about $18,235, a liability on the books because the billing is ahead of the work. Had the billing been lower than revenue earned, the project would be underbilled, which is an asset and a warning sign that cash is lagging behind the work. This guide uses simple numbers and cannot cover the accounting treatment in full, so confirm the method and the presentation with your CPA. Our construction WIP report guide explains how the report works, and our construction job costing guide covers where the cost numbers come from.

What can you automate in pay applications?

The slow part of a pay application is gathering progress. Someone has to find out how much of each line is complete, usually by phoning superintendents and subcontractors, then type it into a spreadsheet and check the totals. If field quantities already live in a system such as HCSS HeavyJob, the percent complete for many lines can come from installed quantities instead of memory, which is the same data job costing uses. Our guide to connecting HeavyJob data to your ERP covers moving those quantities without re-keying.

From there, the mechanical steps can run automatically: carrying previous amounts forward, calculating completed and stored to date, applying the retainage rule, reconciling the summary to the detail and flagging lines that would exceed 100% or that jumped unusually since the last application. A person should still review progress for the lines that matter, confirm stored materials paperwork and approve before it goes out, because the application is a certification. Our construction automation guide describes the pattern, and the CMES construction reporting case study shows one real project that connected field, ERP and reporting data. For cash timing after the application is sent, read about accounts receivable automation and cash flow forecasting.

What mistakes hold up payment?

The summary and detail not reconciling is the classic. Close behind are billing for stored materials without the contract language or the paperwork, applying the wrong retainage rate or applying it inconsistently, billing more than 100% of a line, forgetting that approved change orders need their own lines, and sending the application late in the billing cycle. A less visible mistake is front-loading the schedule of values so aggressively that the owner pushes back for months, which damages the relationship for the whole job.

Another quiet problem is losing track of what was billed against what was earned. If nobody compares the pay application with cost-to-date and the projected final cost, overbilling can look like a healthy cash position right up to the point where the remaining work costs more than the remaining contract. Pull the two reports side by side at least monthly.

Frequently Asked Questions

What is a schedule of values?

A schedule of values is a breakdown of the contract price into line items, usually by trade or specification division, agreed by the contractor and owner before work starts. Pay applications bill against those lines.

What is the AIA G702?

The G702 is the AIA Application and Certificate for Payment, the summary sheet of a pay application. It pulls totals from the G703 continuation sheet, subtracts retainage and previous payments and shows the current payment due.

What is the AIA G703?

The G703 is the continuation sheet that lists every schedule of values line with its scheduled value, previous and current work, stored materials, total completed to date, percent complete, balance to finish and retainage.

What is retainage in construction?

Retainage is a percentage of each payment that the owner holds back until the work is complete or a milestone is reached. The rate, reductions and release terms come from the contract and may be limited by law.

Can you bill for stored materials?

Only if the contract allows it. Owners typically require invoices, photos, proof of insurance and secure storage. Check your contract and supply the paperwork with the application.

How is percent complete calculated on a pay application?

On the G703, percent complete is total completed and stored to date divided by the scheduled value for each line. How the contractor determines the work completed, by quantities, cost or inspection, depends on the contract and the line.

What is the percentage of completion method?

It is an accounting method for long-term contracts. In the cost-to-cost form, percent complete equals costs incurred to date divided by total estimated costs, and revenue recognized equals that percent times the contract price. Confirm treatment with your CPA.

What is the difference between a pay application and revenue recognition?

A pay application is a billing request to the owner. Revenue recognition is an accounting decision about how much revenue has been earned. The gap between billings and revenue earned appears as overbilling or underbilling on the WIP report.

Why do pay applications get rejected?

Common reasons are that the summary does not tie to the detail, retainage is wrong, stored materials lack documentation or contract support, a line exceeds 100%, or change orders are not shown properly.

Can pay applications be automated?

Mechanical steps such as carrying forward previous amounts, applying retainage, reconciling totals and flagging odd jumps can be automated, and field quantities can feed percent complete. A person should review progress and approve the certification.

Bottom Line

The schedule of values sets the terms of every pay application that follows, and the G702 and G703 only work when they agree. Keep the schedule balanced, document stored materials, apply retainage consistently and compare what you bill with what you earn. If you want field progress, billing and reporting connected, see our AI workflow automation and AI and ERP integration services.

Keyur Ajmera
President & Partner, Commerce Pundit

I’m Keyur Ajmera, President & Partner at Commerce Pundit, where I bring over 17 years of experience at the intersection of digital commerce, technology, and AI innovation. Throughout my career, I’ve worked with industry leaders like Amazon, GE, Beats by Dre, NBC, CBS, the LAPD, and LA County, delivering transformative solutions that drive real impact. At Commerce Pundit, I lead a talented team across technology, operations, customer success, and strategy—all focused on helping our clients achieve extraordinary results. Under my leadership, we’ve grown our business to 9 figures, powered by a relentless commitment to innovation, AI-driven solutions, and customer success. Let’s connect and explore how we can harness technology and AI to elevate your business to new heights.

What our clients says

An assemblage of our most passionately crafted works alongside forward-thinking clients and friends throughout the years.

Eric Truong
Eric Truong CEO, LA Nails Supply
" Commerce Pundit’s collaboration created a stunning website representing our beauty nails business. Their SEO strategies boosted rankings and traffic.Transparent communication and prompt feedback incorporation exceeded expectations. "

0%

Increase in orders

0%

Increase in revenue

0%

Increase in site traffic

Contact Us